Reconstruction of Ramp #8 (MD Rte. 2 SB to MD Rte. 100 WB)



SHA Contract #AX9456114

 

Glen Burnie, Anne Arundel County, MD

 

Cost of the project - $1,923,300, completed work as a general contractor.

 

The scope of work included the emergency repairs to an existing ramp caused by excessive rainfall. The ramp was closed to traffic via a temporary detour. Support of excavation (sheet piling) was driven and the existing roadway was excavated for the installation of a new storm drain pipe across the ramp. The work was completed in two phases to allow traffic on the ramp during the holiday season.