Masonville Storm Drain Relocation
The scope of work included the design and installation/removal of support of excavation (sheet piling) for the excavation and relocation of an existing storm drain.
MPA Contract #508519
Port of Baltimore – Fairfield, Baltimore City, MD
Cost of the project - $487,500, completed work as a subcontractor